June 2022 Quarterly Report Released
29 July 2022
Clean TeQ Water is pleased to provide an update on our activities for the quarter ending 30 June 2022.
Highlights for this Quarter Include
- Quarterly cash receipts of $2.5m up by 60% from the previous quarter ($1.6m)
- New $5 million contract signed with Power and Water Corporation (PWC) for a Bore Water Treatment Plant in the Northern Territory
- Ordos flagship 12,000 tons/day BIONEX™ nitrate removal project handed over to customer for ongoing operation of the main resin circuit
- Continued progress across all projects under implementation
- NematiQ progressed towards field piloting by converting recently produced Graphene Membrane sheets into membrane elements and skids
- Total FY21/22 cash receipts of $9.2m